creating issues¶
Estimate¶
Story points (SP)¶
Story points: 1, 2, 3, 5, 8, 13
One story point is 4 hours of working time for each person. That means if there is a 2 hour meeting with 5 people the issue at least takes 10 hours so that would be 2 - 3 Story points
Scope¶
Contains:
Planning of the issue
Execution of the issue
Meetings
Testing